Work Breakdown Structure
Broken down into achievable tasks
Tasks can be broken into subtasks
All tasks must add up to its parent subtask
A task that has subtasks, must have more than 1 and must be labelled correctly.
Subtasks at the lowest levels are called work-packages. (if task have no subtasks, that task is considered a work-package.)
WBS shows what has to be done in the project but never shows you when.